Villawood Plaza
882-890 Woodville Rd, Villawood, NSW
Mixed-use development consists of 88 spacious apartments and 2,500 m2 retail, spread over 2 basements, retail ground and 7 residential floors.
Construction cost $27M
Scope of work:
Value engineering the old structural design
Provide construction feasibility
Structurally redesign the building including the shoring system
Achievements:
Utilising our experience and innovative approach, we saved our client a $1.8M from the construction budget in addition to reduce the PT tonnage by 35%.

 

Community Development
Arnold Ave, Kellyville, NSW
Consists of 11,700 sqrt. meter built-up area, spread over 2 basements, ground and 2 floors.
Construction cost $24M
Scope of work:
Structural engineering design
Vibration analysis
Construction feasibility
Value Engineering
Achievements:
Using aninnovative solution, we designed a columnless hall 30.5X27.5m reaching safe structural integrity, comfort vibration and deflection.

Penrith Gateway
114-116 Station St, Penrith, NSW
Gateway residential development consists of 29 boutique apartments, spread over 2 basements, ground and 7 floors.
Construction cost $8.0M
Scope of work:
Change the structural system for the superstructure from walls to columns system considering that the construction already reach ground floor.
Risk assessment for the existing ground transfer floor.
Construction feasibility
Value Engineering
Achievements:
Utilising our experience and innovative approach, we changed the structural system for the superstructure to small columns system which result in reduce the construction budget by a $0.90M.

Basement addition and Heritage extension
Northcote, Melbourne
$5M extension development project for a 150 years old heritage building consisting of a basement addition (partly under the existing heritage building), four floors, and roof as swimming pool. It was a challenging job, where we succeeded in overcome all the difficulties and the poor soil conditions (class P site), by implementing high-tech structural design and construction methods. We designed and documented a top-down construction to ensure stability and integrity of the heritage building